31/03/2023: Brooklyn lights -O/T/C intersection update from Fulton Hogan the WCC contractor

Carl from Brooklyn Residents Association Incorporated

Brooklyn lights update (31/03/2023) - O/T/C intersection Good morning. Here is the latest update from Fulton Hogan. Hang in there, the contractiors are nearly done ...

"Hi all,

Just an update on the intersection improvements which are finally drawing to a close. In between the rain this week we managed to pour the new kerb and channel on the final corner outside the old wish skin spa building. With a clear run of weather and no other disruptions, this corner should be completed by the end of next week – Thursday 6 April. Until then, some of the pedestrian crossing will likely be closed until the light poles can be reinstated.

Then we’ll have to revisit the corner outside Salty Pidgin to install some sub-soil drainage that will help with the water issues. These were only decided upon after we’d initially completed that corner. We’ve also been requested to attend to some failures in the road while we’re there. These patches are right in the intersection and different to the ones further up Todman Street, which were finally remediated recently. We will do our best to keep the pedestrian crossing here open, but the patches are extremely close so it may not be possible from a safety perspective.

The final requirement for us and our sub-contractor is to install an overhanging traffic light pole and install some new line marking. Conversations are on-going as to whether the light pole installation takes place at night or can be done during the day, but it is scheduled to take place after the other remaining work. The vast majority of line marking will be done at night and will have little impact. However, please remember to drive carefully while everyone gets used to the new layout.

Our estimated new finish date is Friday 21 April. I’m sure you’re all eager to see us gone but I do have to advise that, following completion of the intersection, we will have a crew starting work at the top end of Todman Street, uphill from the kindergarten, and into Mitchell Street preparing for eventual road resurfacing sometime between October 2023 and April 2024.

Thanks,

Michael “Chewy” Chew | Programme and Delivery Manager | Fulton Hogan Ltd"

Image
More messages from your neighbours
3 days ago

Poll: Is the increase in disability parking fines fair?

The Team from Neighbourly.co.nz

In October, the fine for parking in a designated mobility car park without a permit has jumped from $150 to $750—a 400% increase!

The goal is to keep these spaces open for those who truly need them. Do you think this big increase in the fine is fair? Share your thoughts below.

Image
Is the increase in disability parking fines fair?
  • 89.4% Yes, it's fair
    89.4% Complete
  • 9.8% No, it's unreasonable
    9.8% Complete
  • 0.8% Other - I'll share below
    0.8% Complete
2359 votes
1 day ago

Just dough it

The Team from Resene ColorShop Basin Reserve

With three basic ingredients and a bit of creativity, you can give old containers new life with Resene testpots.

Find out how to create your own with these easy step by step instructions.

Image
1 day ago

Do you recognise any of these bikes? 🚲

The Team from Wellington District Police

Wellington Police have recently recovered eight bikes and would like to reunite them with their owners.

If you believe one is yours, head to the Wellington Police Station to retrieve your property. Make sure to bring either a proof of purchase or serial number to prove ownership.

To have a proper look, click on any image to enlarge it.