Brooklyn lights update (31/03/2023) - O/T/C intersection Good morning. Here is the latest update from Fulton Hogan. Hang in there, the contractiors are nearly done ...

"Hi all,

Just an update on the intersection improvements which are finally drawing to a close. In between the rain this week we managed to pour the new kerb and channel on the final corner outside the old wish skin spa building. With a clear run of weather and no other disruptions, this corner should be completed by the end of next week – Thursday 6 April. Until then, some of the pedestrian crossing will likely be closed until the light poles can be reinstated.

Then we’ll have to revisit the corner outside Salty Pidgin to install some sub-soil drainage that will help with the water issues. These were only decided upon after we’d initially completed that corner. We’ve also been requested to attend to some failures in the road while we’re there. These patches are right in the intersection and different to the ones further up Todman Street, which were finally remediated recently. We will do our best to keep the pedestrian crossing here open, but the patches are extremely close so it may not be possible from a safety perspective.

The final requirement for us and our sub-contractor is to install an overhanging traffic light pole and install some new line marking. Conversations are on-going as to whether the light pole installation takes place at night or can be done during the day, but it is scheduled to take place after the other remaining work. The vast majority of line marking will be done at night and will have little impact. However, please remember to drive carefully while everyone gets used to the new layout.

Our estimated new finish date is Friday 21 April. I’m sure you’re all eager to see us gone but I do have to advise that, following completion of the intersection, we will have a crew starting work at the top end of Todman Street, uphill from the kindergarten, and into Mitchell Street preparing for eventual road resurfacing sometime between October 2023 and April 2024.

Thanks,

Michael “Chewy” Chew | Programme and Delivery Manager | Fulton Hogan Ltd"

Image
More messages from your neighbours
6 hours ago

New Year, New Questions You Won’t Solve!

Riddler from The Neighbourly Riddler

I get smaller every time I take a bath.

What am I?

Do you think you know the answer to our daily riddle? Don't spoil it for your neighbours! Simply 'Like' this post and we'll post the answer in the comments below at 2pm.

Want to stop seeing riddles in your newsfeed?
Head here and hover on the Following button on the top right of the page (and it will show Unfollow) and then click it. If it is giving you the option to Follow, then you've successfully unfollowed the Riddles page.

Image
6 hours ago

Clothesline upgrade

Resene

Turn a tired old clothesline into a stylish garden feature that brings joy to the chore of getting your washing out in the sun. Finish in Resene Waterborne Woodsman Crowshead. Find out how to create your own with these easy step by step instructions. Find out more

Image
6 hours ago

Explore more, worry less at Ryman

The Team from Ryman Healthcare

Pack your bags, hit the open road, or set sail on your next big adventure. With Ryman’s lock-and-leave-style living, you’re free to explore without worrying about home maintenance or security.

While you’re off enjoying life, we’ll take care of everything back home – from mowing the lawns to watering the garden, pulling weeds, and even cleaning the windows.

Ryman residents are free to embrace adventure because they're not tied down with home maintenance stress and security worries. They're rediscovering lost passions and plunging headfirst into new ones whenever they feel like it.

Click find out more to discover the lifestyle.
Find out more

Image