Upgrading roads around Christchurch stadium no longer 'paused', despite mayor's moves to delay project

Nicole Mathewson Reporter from The Press

From reporter Steven Walton:

Work has resumed on a hotly-debated $33 million upgrade to roads around Christchurch's planned stadium.

Residents now have until the end of the month to share their views on the project.

More than 850 submissions have already been made – making the project the council’s second most popular consultation of the year. The future of the stadium itself was the most popular.

The $33m upgrade has not been supported by new mayor Phil Mauger, who has suggested the money would be better spent fixing roads in the east or going towards the $683m cost of the stadium.

Nearly two weeks ago, the council said work on the project was paused and Mauger said that was a consequence of his wish to not proceed with the work.


On Tuesday, the newly-elected council was briefed behind closed doors about the project.


Council chief executive Dawn Baxendale said the briefing to the council explained the project will improve pedestrian safety and traffic management while also replacing “outdated” three waters networks around the stadium.

Following the briefing, work on the project has resumed.


That means the public consultation can be finished and staff can consider the responses.

A council spokesperson said staff would then make changes to the proposal where it can. After that, it will make a recommendation to a hearings panel that is expected to convene in February next year.

The panel will then make a final recommendation to the council in March, when the council will effectively decide whether the project continues.

The Christchurch City Council launched consultation on the scheme on the first day of Mauger’s mayoralty and released its proposed plans covering Lichfield, Madras, Tuam and Barbadoes streets.

Footpaths would be widened to up to 5.8m on some streets, speeds lowered to 10kph or 30kph, car parks taken away and room allowed for cycle lanes, gardens and outdoor dining.


But businesses along one of the routes were not happy with the plans, as they did not want to lose parking.

The two options for Lichfield St involve the loss of some, or all 72, car parks.


The council’s consultation document said the upgrades were designed to cater for large influxes of traffic and pedestrians attending events at the stadium, Te Kaha.

If approved, the work would start some time next year and be completed by 2026, when Te Kaha is due to open.

Mauger said in October he wanted to delay the work on the surrounding streets until after the stadium was built.

“I would rather, as a ratepayer, drive down the streets as they are and pay that $24m (sic) off the stadium.”

While Mauger said the cost was $24m, the council’s consultation document said it was $33m.

Mauger said the work should be done, but only “when people come and we get more money”.

“You’ve got to cut your cloth to suit the budget.”

More messages from your neighbours
J
2 days ago

BRAND NEW. Paid $275

Judith from Northwood

Only a week old Bought from. STIHL

Not Suitable for Us

Selling At. $150

Must Pick Up from Northwood Ch Ch

STIHL. LAWN. EDGER and 3 Spools new Skin Only

Queries

Phone no. 0274487461. Judith

2 days ago

Poll: Do you think banning gang patches is reasonable?

The Team from Neighbourly.co.nz

With the government cracking down on gangs, it is now illegal for gang members to display their insignia in public places whether through clothing or their property.

This means arrests can be made if these patches are worn in places like restaurants, shops, on public transport or ferries, and on airplanes. Arrests were made recently at a funeral.

Do you think this ban is reasonable?

Image
Do you think banning gang patches is reasonable?
  • 75.8% Yes
    75.8% Complete
  • 22.8% No
    22.8% Complete
  • 1.4% Other - I'll share below
    1.4% Complete
2001 votes
14 hours ago

Raspberry plants $10-20ea and Thornless Blackberry plants $10-25ea

Richard from Rangiora

This sale is for raspberry plants ($15 or $20 each depending on size) and thornless blackberry plants ($25 or $20 each depending on size).

Discounts for bulk purchases.
All plants are in top-quality soil.

All raspberries have been transplanted from existing Clutha, Heritage and Lewis varieties. They produce fantastic raspberries. The thornless blackberries are Black Satin.

Pick up in Rangiora. However, for a $80 purchase, I'm happy to deliver within 30 minutes of Rangiora for an extra $10.

*Pick up my free ‘How To Grow Raspberries’ guide with your purchase.*

We need to exchange mobile numbers before pickup.