486 days ago

Bid to move river away from town

Nicole Mathewson Reporter from The Press

From local democracy reporter Brendon McMahon:

An application has been lodged to divert the Waiho (Waiau) River at Franz Josef as part of the stalled $12.5 million north bank flood protection scheme.

The West Coast Regional Council is applying to itself for the temporary diversion of the river from below the State Highway 6 bridge to the glacial moraine, where the Waiho and Tatare riverbeds converge.

“The proposed diversion is to allow gravel extraction, and stopbank construction ... in dry riverbed and to prevent any potential scour of temporary works during the construction phase,” consultant Davis Ogilvie says on behalf of the council.

The applications relate to two separate flood protection works under the stage one north bank scheme: the Franz Josef stopbank and the Tatare River stopbank.

The application notes that the Waiho riverbed has been aggrading at 18cm a year in recent decades.

Flood protection improvement was deemed a priority following the 2016 flood causing after it caused $30m of damage. In March 2019 the state highway bridge was swept away following 400mm of rain was also a factor.

“A $24m package was approved by the Government in July 2020, as part of the Covid-19 economic stimulus package. The work included $18m for rock embankments on the north and south banks, and $3.8m to raise the level of the highway bridge.”

The regional council let a contract to Greymouth contractor MBD for the north bank work nearly a year ago.

The proposed river diversion is from the bridge down past the township and beyond the Westland District Council's wastewater treatment plant.

Temporary diversion of water for up to two years within the bed of the Waiho River is also sought.

The main project is currently stalled after the regional council failed to get affected party approval from the Scenic Circle Hotel Group.

In the latest application the three affected parties identified are the Department of Conservation (DOC), Fish and Game, and Te Rūnanga o Makaawhio.

DOC had already responded it had no concerns apart from the unprotected bank on the south side of the river below Canavans Knob.

DOC said the unprotected bank below Canavans had been “a real safety issue” for property and life in a number of recent floods.

“If the river is trained away from the north — then the probability of it being more likely to impact this bank is increased.”

The department said it would like to see armouring put in place and the Canavans stopbank upgraded significantly to mitigate the risk prior to the river diversion/training.

“This isn't so much a conservation concern as a community and Civil Defence issue,” DOC said.

Davis Ogilvie notes consent for the north bank scheme was independently lodged on March 3 last year and was currently on hold.

Likewise, an application for gravel extraction associated with the stopbanks construction had been independently lodged last month but was also on hold.

Consent to disturb the bed and banks of the Waiho River to the Tatare stopbank was granted in October 2022 along with a discharge consent for incidental sediment into the Waiho River from the Tatare stopbank construction.

Land use consent had already been sought to raise all existing flood protection banks on the north side by 2m, along with consent to extract gravel from the dry riverbed for raising the existing stopbanks and extending them.

More messages from your neighbours
17 hours ago

Happy Friday y'all! Here's the last riddle of the week!

Riddler from The Neighbourly Riddler

I am an instrument through which sounds are made, and yet, I am not something that can be played. What am I?

Do you think you know the answer to our daily riddle? Don't spoil it for your neighbours! Simply 'Like' this post and we'll post the answer in the comments below at 2pm.

Want to stop seeing riddles in your newsfeed?
Head here and hover on the Following button on the top right of the page (and it will show Unfollow) and then click it. If it is giving you the option to Follow, then you've successfully unfollowed the Riddles page.

Image
5 days ago

Why are ghosts such bad liars?

The Team from Neighbourly.co.nz

...You can see right through them.

No, we haven't lost the plot! July 1st is International Joke Day and because laughter is good for your body, we want to get involved.

So, go on, jokers! Share your best joke below...

Image
5 hours ago

Pressure on council to protect Hokitika from flooding

Nicole Mathewson Reporter from The Press

By local democracy reporter Brendon McMahon:

Earthworks should begin along Hokitika's Gibson Quay next week on a delayed flood bank build.

The clock has been ticking on the Hokitika River protection project since last December when West Coast Regional Council awarded a contract but then had to wait on KiwiRail to sign the project off.

Council, in an extraordinary meeting on Thursday (July 4), approved extra costs in response to KiwiRail requirements above the original tender price.

Contractor Henry Adams was awarded the tender at the end of 2023 after last winter completing the first stage of the project, behind Westland Milk Products, and adjoining the river.

The new section runs along the railway line and Gibson Quay from Westland Milk Products down to the Hokitika Bridge.

It also adjoins the Wadeson Island and Hokitika River bank whitebaiting area.

Council chairperson Peter Haddock said the pressure is now on to finish the new flood bank within two months - with the local whitebaiting season due to start on September 1.

"It's been delayed and once again it's been a concern of council in getting through the project … I do understand that Kiwi Rail have to look after their asset," Haddock said.

In the meantime the community remained "vulnerable" to the river.

"The bulk of the works have got to be done before the whitebait season … that project will be underway immediately next week - that will be a good bit of protection works for Hokitika," Haddock said.

Dubbed '1B,' the project is the second of a suite of staged Kanoa approved flood resilience works costing several million dollars.

These will eventually improve protection to the entire Hokitika residential and business area from Kaniere to the CBD.

Haddock said KiwiRail had sought adjustment to the original contract scope.

"It had been let to Henry Adams Contracting subject to approval from KiwiRail, which has taken over nine months - because it was let before Christmas," Haddock said.

"They've finally come back and there's more work to do to protect their network."

The extraordinary meeting was required to tick off the cost of "more earthworks" and drainage in response to KiwiRail.

"There was a significant cost but it was below the budget that was allowed for the project," Haddock said.

This amounted to about $200,000 below their original budget contingencies.

"The contract is still under budget."

Haddock said the adjusted costs "were still competitive" and the council was satisfied with a staff recommendation on that basis.