Back
600 days ago

New West Coast plan draws 500 submissions

Nicole Mathewson Reporter from The Press

From local democracy reporter Brendon McMahon:

The Te Tai o Poutini Plan (TTPP) has drawn about 500 submissions.
Submissions opened on July 21 and formally closed on Friday after two extensions. Now the work begins.

The draft which will combine the West Coast's three district plans into one is acknowledged as a 'test case' for the Government's RMA reform.

Grey District Council district planner Michael McEnaney, who led the submission for the largest Coast council, said it had taken months for Grey alone, but the bigger process was only really beginning now submissions were in.

The draft had its "pros and cons" but a much bigger process to work through the submissions had to begin, McEnaney said.
"The hard part is starting, where everyone in the world gets to pull it apart and have their say."

They awaited with interest to see what "big players" like the Department of Conservation and Forest and Bird had to say.

"I think most people involved in the process are waiting with bated breath. The submissions now are going to shape where the plan is going to head. There's so much water under the bridge yet."

TTPP project manager Jo Armstrong said staff at the West Coast Regional Council had a big day yesterday counting and logging submissions into a format for summary.

The 500 or so submissions reflected a good level of interest given the region's comparatively low population, she said.

"While we got lots of submissions, it doesn't mean it's a bad plan."
All submissions would be summarised into topic areas, and presented to the TTPP Committee to consider, by about January.

"It's a huge amount to process and then summarise."

A 'resubmissions' period would then be called for those who had already made formal submissions. This would give registered submitters the opportunity to "see the lie of the land" reflected in the submissions to the plan.

It was likely the TTPP Committee would convene pre-hearing meetings to bring together common topics from the submissions.

A formal hearing panel was expected to be convened in the second half of 2023.

Armstrong said she expected it would be over a year before the committee received any recommendations from the hearing panel.

McEnaney said the bulk of his time since July had been spent writing the submission for Grey.

"It's 800 and something pages and I must have read it cover to cover three times in the last three months."

It had also involved significant time coordinating in-house and other local experts to address particular areas in the plan, as well as work-shopping elected members in a democratic approach to a whole plan submission from Grey.

McEnaney said he could not give a page number, as it was across a spreadsheet, but the Grey District contribution was "massive".

There had been issues as parts of the TTPP had also evolved since submissions opened -- with the later chapter on sites and areas of significance to Māori throwing implications for earlier chapters such as rural and subdivision.

*Public interest journalism funded through NZ On Air

More messages from your neighbours
6 days ago

Why are ghosts such bad liars?

The Team from Neighbourly.co.nz

...You can see right through them.

No, we haven't lost the plot! July 1st is International Joke Day and because laughter is good for your body, we want to get involved.

So, go on, jokers! Share your best joke below...

Image
18 hours ago

Controversial West Coast landfill granted extension to fix issues

Nicole Mathewson Reporter from The Press

By local democracy reporter Brendon McMahon:

A controversial West Coast private landfill under Environmental Protection Authority (EPA) watch is being given more time to fix water issues following "adverse weather".

The EPA has granted Taylorville Resource Park (TRP) an extension of a few weeks to meet the requirements of a three month abatement notice slapped on the site in March.

It came after the West Coast Regional Council asked the authority in February to take over its environmental compliance investigation of the Coal Creek landfill, 5km east of Greymouth.

The council was plagued with complaints about the landfill site throughout 2023.

These ranged from an overwhelming stench forcing neighbours to stay indoors, alleged asbestos generated dust, and water leaching from the site into a roadside drain.

After the authority took over investigations in February, it found leachate from the landfill had been allowed to spill from the site via an adjoining waterway.

Under the subsequent abatement, TRP were given three months to comply, ending June 14.

Investigations manager Jackie Adams said compliance officers have since visited the site and found TRP have made "significant progress".

However, the work required has not been completed due to "adverse weather conditions" during the abatement period, Adams said.

Because of this, the authority had yet to determine the final outcome of its investigation.

"Our officers will be returning to the site again in the coming weeks," Adams said.

"Once this inspection has been completed, we will determine if all the conditions of the notice have been met before considering any next steps."

LDR has asked the authority what type of weather factor was at play.
"We understand that there were poor weather conditions in April that affected TRP's ability to install the waterproof lining of the new storage pond," Adams said.

The authority recognised the future of the site as "an important issue for people in the region".

It continued to work with TRP to ensure compliance with the abatement, he said.

"Under the Resource Management Act, the EPA has specific enforcement functions to assist and intervene in an enforcement action of a council."

Adams said they will provide a further update when they have completed their follow-up inspection and confirmed any next step.

West Coast Regional Council Regulatory and Policy group manager Jocelyne Allen said they were keeping a watch on the site to ensure an "appropriate level of enforcement" in line with "the level of environmental effects".

Allen was asked to expand in what was meant by an appropriate level of enforcement.

She said the council was "using its discretion" while working through its enforcement strategy.

This was to ensure relevant treatment of the site from a compliance perspective, she said.

Allen said they expected an update from the EPA by mid-July.

The council had several options to consider, under the Resource Management Act, beyond the EPA's findings.

Those could include anything "from a warning right up to prosecution," Allen said.

The council also had the power to issue notices with conditions plus interim and enforcement orders.

Allen said they were constantly evaluating the best options, but the council had not yet taken action to say "it can't operate".

"We wouldn't just be able to shut the site down at this stage."

Allen said more recent consent applications from TRP may yet go to a public hearing, but council had to assess if the impacts were "more than a minor environmental effect" before making a hearing decision.

Allen said that could also be circumvented if the applicant themselves requested a public hearing.

TRP has been approached by LDR. Questions included if it anticipates meeting the extended abatement period, and if it would be happy for a public hearing.

1 day ago

Pressure on council to protect Hokitika from flooding

Nicole Mathewson Reporter from The Press

By local democracy reporter Brendon McMahon:

Earthworks should begin along Hokitika's Gibson Quay next week on a delayed flood bank build.

The clock has been ticking on the Hokitika River protection project since last December when West Coast Regional Council awarded a contract but then had to wait on KiwiRail to sign the project off.

Council, in an extraordinary meeting on Thursday (July 4), approved extra costs in response to KiwiRail requirements above the original tender price.

Contractor Henry Adams was awarded the tender at the end of 2023 after last winter completing the first stage of the project, behind Westland Milk Products, and adjoining the river.

The new section runs along the railway line and Gibson Quay from Westland Milk Products down to the Hokitika Bridge.

It also adjoins the Wadeson Island and Hokitika River bank whitebaiting area.

Council chairperson Peter Haddock said the pressure is now on to finish the new flood bank within two months - with the local whitebaiting season due to start on September 1.

"It's been delayed and once again it's been a concern of council in getting through the project … I do understand that Kiwi Rail have to look after their asset," Haddock said.

In the meantime the community remained "vulnerable" to the river.

"The bulk of the works have got to be done before the whitebait season … that project will be underway immediately next week - that will be a good bit of protection works for Hokitika," Haddock said.

Dubbed '1B,' the project is the second of a suite of staged Kanoa approved flood resilience works costing several million dollars.

These will eventually improve protection to the entire Hokitika residential and business area from Kaniere to the CBD.

Haddock said KiwiRail had sought adjustment to the original contract scope.

"It had been let to Henry Adams Contracting subject to approval from KiwiRail, which has taken over nine months - because it was let before Christmas," Haddock said.

"They've finally come back and there's more work to do to protect their network."

The extraordinary meeting was required to tick off the cost of "more earthworks" and drainage in response to KiwiRail.

"There was a significant cost but it was below the budget that was allowed for the project," Haddock said.

This amounted to about $200,000 below their original budget contingencies.

"The contract is still under budget."

Haddock said the adjusted costs "were still competitive" and the council was satisfied with a staff recommendation on that basis.