Back
602 days ago

Coal tar dump opened near Greymouth

Nicole Mathewson Reporter from The Press

From local democracy reporter Brendon McMahon:

The West Coast Regional Council has agreed to a consent change to Taylorville Resource Park Ltd to allow coal tar and pitch to be disposed of at the existing landfill site.

The change allows construction of an additional lined asbestos cell.

Consents and compliance manager Colin Helem told the council's resource management committee meeting the coal tar and pitch was in common use for road making until the 1970s, "and does have the potential for leachate".

The cell to be constructed would provide containment of the material from leaching into ground water.

Councillor Peter Ewen asked if that meant bitumen could be dumped in a clean fill site, which Helem confirmed.

Councillor Peter Haddock clarified if the new dump was above the existing Greymouth water supply treatment site at Coal Creek, which Helem affirmed.

Meanwhile, the problem with river and stream beds on the West Coast continually building up with gravel and not being managed was also a discussion point.

Westreef Services had been granted a non-notified resource consent to disturb the dry bed of the Punakaiki River to remove gravel.

Councillor Brett Cummings wondered why this was allowed when water courses on the Barrytown Flats, for example, was far more urgent for gravel management, with "culverts overflowing".

"Why are we allowing gravel take from the Punakaiki River?"

Helem said council simply processed the requests before it.

"We don't have control over getting applicants going to rivers we want them to get gravel out of."

Cummings said believed those seeking gravel would "find their own way" to viable gravel sources if they received some direction.

Photo: The historic Broadcasting House in Greymouth is currently being demolished. With other major demolitions pending in the area and the need for safe disposal of demolition materials including asbestos, along with old coal tar bitumen, several sites including the one at Taylorville are being opened up. The 1930s Public Works era Broadcasting House was built after the 1929 Murchison Earthquake and has proved a substantial demolition challenge in the past 10 days.

*Public interest journalism funded through NZ On Air

More messages from your neighbours
6 days ago

Why are ghosts such bad liars?

The Team from Neighbourly.co.nz

...You can see right through them.

No, we haven't lost the plot! July 1st is International Joke Day and because laughter is good for your body, we want to get involved.

So, go on, jokers! Share your best joke below...

Image
18 hours ago

Controversial West Coast landfill granted extension to fix issues

Nicole Mathewson Reporter from The Press

By local democracy reporter Brendon McMahon:

A controversial West Coast private landfill under Environmental Protection Authority (EPA) watch is being given more time to fix water issues following "adverse weather".

The EPA has granted Taylorville Resource Park (TRP) an extension of a few weeks to meet the requirements of a three month abatement notice slapped on the site in March.

It came after the West Coast Regional Council asked the authority in February to take over its environmental compliance investigation of the Coal Creek landfill, 5km east of Greymouth.

The council was plagued with complaints about the landfill site throughout 2023.

These ranged from an overwhelming stench forcing neighbours to stay indoors, alleged asbestos generated dust, and water leaching from the site into a roadside drain.

After the authority took over investigations in February, it found leachate from the landfill had been allowed to spill from the site via an adjoining waterway.

Under the subsequent abatement, TRP were given three months to comply, ending June 14.

Investigations manager Jackie Adams said compliance officers have since visited the site and found TRP have made "significant progress".

However, the work required has not been completed due to "adverse weather conditions" during the abatement period, Adams said.

Because of this, the authority had yet to determine the final outcome of its investigation.

"Our officers will be returning to the site again in the coming weeks," Adams said.

"Once this inspection has been completed, we will determine if all the conditions of the notice have been met before considering any next steps."

LDR has asked the authority what type of weather factor was at play.
"We understand that there were poor weather conditions in April that affected TRP's ability to install the waterproof lining of the new storage pond," Adams said.

The authority recognised the future of the site as "an important issue for people in the region".

It continued to work with TRP to ensure compliance with the abatement, he said.

"Under the Resource Management Act, the EPA has specific enforcement functions to assist and intervene in an enforcement action of a council."

Adams said they will provide a further update when they have completed their follow-up inspection and confirmed any next step.

West Coast Regional Council Regulatory and Policy group manager Jocelyne Allen said they were keeping a watch on the site to ensure an "appropriate level of enforcement" in line with "the level of environmental effects".

Allen was asked to expand in what was meant by an appropriate level of enforcement.

She said the council was "using its discretion" while working through its enforcement strategy.

This was to ensure relevant treatment of the site from a compliance perspective, she said.

Allen said they expected an update from the EPA by mid-July.

The council had several options to consider, under the Resource Management Act, beyond the EPA's findings.

Those could include anything "from a warning right up to prosecution," Allen said.

The council also had the power to issue notices with conditions plus interim and enforcement orders.

Allen said they were constantly evaluating the best options, but the council had not yet taken action to say "it can't operate".

"We wouldn't just be able to shut the site down at this stage."

Allen said more recent consent applications from TRP may yet go to a public hearing, but council had to assess if the impacts were "more than a minor environmental effect" before making a hearing decision.

Allen said that could also be circumvented if the applicant themselves requested a public hearing.

TRP has been approached by LDR. Questions included if it anticipates meeting the extended abatement period, and if it would be happy for a public hearing.

1 day ago

Pressure on council to protect Hokitika from flooding

Nicole Mathewson Reporter from The Press

By local democracy reporter Brendon McMahon:

Earthworks should begin along Hokitika's Gibson Quay next week on a delayed flood bank build.

The clock has been ticking on the Hokitika River protection project since last December when West Coast Regional Council awarded a contract but then had to wait on KiwiRail to sign the project off.

Council, in an extraordinary meeting on Thursday (July 4), approved extra costs in response to KiwiRail requirements above the original tender price.

Contractor Henry Adams was awarded the tender at the end of 2023 after last winter completing the first stage of the project, behind Westland Milk Products, and adjoining the river.

The new section runs along the railway line and Gibson Quay from Westland Milk Products down to the Hokitika Bridge.

It also adjoins the Wadeson Island and Hokitika River bank whitebaiting area.

Council chairperson Peter Haddock said the pressure is now on to finish the new flood bank within two months - with the local whitebaiting season due to start on September 1.

"It's been delayed and once again it's been a concern of council in getting through the project … I do understand that Kiwi Rail have to look after their asset," Haddock said.

In the meantime the community remained "vulnerable" to the river.

"The bulk of the works have got to be done before the whitebait season … that project will be underway immediately next week - that will be a good bit of protection works for Hokitika," Haddock said.

Dubbed '1B,' the project is the second of a suite of staged Kanoa approved flood resilience works costing several million dollars.

These will eventually improve protection to the entire Hokitika residential and business area from Kaniere to the CBD.

Haddock said KiwiRail had sought adjustment to the original contract scope.

"It had been let to Henry Adams Contracting subject to approval from KiwiRail, which has taken over nine months - because it was let before Christmas," Haddock said.

"They've finally come back and there's more work to do to protect their network."

The extraordinary meeting was required to tick off the cost of "more earthworks" and drainage in response to KiwiRail.

"There was a significant cost but it was below the budget that was allowed for the project," Haddock said.

This amounted to about $200,000 below their original budget contingencies.

"The contract is still under budget."

Haddock said the adjusted costs "were still competitive" and the council was satisfied with a staff recommendation on that basis.