Culvert Upgrade – Bridge Street, Waikuku Beach

We’re constructing a new stormwater pipe under Bridge Street, from the road-side drain at Reserve Road to the Taranaki Stream.

The existing stormwater infrastructure at the intersection of Reserve Road and Bridge Street is undersized and in poor condition. We’re upgrading this infrastructure to minimise flooding. The work has been awarded to Total Water NZ Ltd.

The work will include
Construction of a new stormwater pipe under Bridge Street, from the road-side drain at Reserve Road to the Taranaki Stream.

Timing of work
Construction will commence early February 2025 and is expected to last up to three weeks.

Traffic impacts
There will be traffic impacts while the works are carried out, prior notification will be provided if any detours are required, otherwise please take care navigating the cones and signs when they are set up.

General impacts

Kerbside collections
Kerbside collections will remain unchanged. Please ensure your bag or bins are in their usual spot on collection day.

Essential services
There will be no planned disruption to your water, wastewater, telephone or power services.

Notice of changes in traffic management
We will do our best to give you enough notice to adjust to any changes in traffic management. Please keep an eye out for more updates.

Hours
All the work will be undertaken between 7.30am and 6pm Monday to Saturday.

Weather
In the event of bad weather or unforeseen circumstances, the work may be delayed.

Safety
Please warn your children of the dangers posed by road works. Ensure they stay well back from the work site and that they follow the directions of the workers.

Noise and dirt
Road work is noisy, dirty business – but please bear with us. We will be doing all we can to minimise the impact on your home/business. Your cooperation and patience will help us get the job done as quickly as possible. All work will be carried out between the stated hours only to help minimise the impact on the community.

Easy does it
Bitumen, concrete and other road repair materials require a bit of care after they are applied. Please treat all new surfaces with extra care following the completion of this project.

Thank you for your patience while we complete this work. For updates check back on this page.

If you have any questions please do not hesitate to contact us.